A little update, have now achieved over 100 units generated, so pretty pleased with performance. Managed to clear silt off intake cylinders, but this must of let air into pipes as the power output dipped a bit down to 937W, though after bleeding the air out for an hour or so with turbines off i got it back up to 1050W. You may notice the hours operational is much higher than should be, but this is only because we have just been running 1 turbine through the night, as there is no-one living up there yet, so didn;t want to take any risks (i.e. not being enough water), though i feel confident now that i could leave it on with no problems.