Feel we have cracked air locking issues now having done extensive re working of the intake design and raising the whole dam. To make sure the pipe is not running horizontal in first 5m and that there is at least 40cm of water from surface to intake. After much trial and error have also installed 2 x honeywell ea122 air vents at the section of pipe that seems to lock out. They are bleeding sufficient air slowly to stop build up and we are getting the power output consistant for several days